Issue Management Methodology for Tracking Project Issues



Learn Management Articles on management-info.biz. Issue Management Methodology for Tracking Project Issues article will help answer your questions on Management Articles.We at management-info.biz specialize in Management Articles. Management Articles at management-info.biz provides the most up to date news and articles. If you have questions please do not hesitate to contact us.

1. What is an Issue?

An issue is an incident, circumstance, problem or inquiry that affects or potentially affects the timely delivery of the project, product or service, it may also impact the quality of deliverables and the cost of production.

Some projects are ongoing and the definition of an issue is a little different. A help desk defines an issue as a request for help that requires a response. A service department keeps track of service requests as issues. A software maintenance group tracks reports of software bugs and enhancement requests as issues.

Because of the impact issues have on a project, product development or ongoing service, issue management is an important aspect in any management methodology. This issue management methodology promises to make the handling of issues a seamless part of your larger scoped methodologies rather than a process separate from them.

It is usually not hard for team members to identify issues, but it is still worth having a working definition of an issue. Remember that the more ambitious your project the more issues will arise.

Action item: The project team must be made aware of what issues are, provide some examples, and ask other team members to provide some examples.

2. Requirements

A central repository of issue information easily accessible to all team members, because it is good for team morale and productivity to know that their issues are being addressed. An automated central repository like Issue Tracker is desirable because it make the issue management and reporting much easier.

Action item: Choose a central repository for your issues.

An issue manager is the person chosen to oversee all issues. It can be the project manager, team leader or another person in a responsible leadership position. The issue manager is responsible for making sure that there is consistent, disciplined and continuous progress made on all issues. The issue manager is accountable to upper management for the progress made on all issues. The issue manager communicates issue progress to the team, upper management and all stakeholders.

Action item: Appoint an Issue Manager and notify the issue manager of their role and responsibilities.

This issue management methodology represents best practice for managing issues. However, the goal is to have a successful project, product development or service, the goal is not to follow a methodology fanatically.

Action item: Adapt the methodology so your project's success is maximized.

3. Steps

3.1 Discovery

Issues can arise at any time. When an issue is discovered it is recorded in the central repository.

It is important to allow issues to be recorded by a broad group of people including team members, upper management, users, customers, stakeholders, vendors and contractors. It is important because if there are barriers to reporting an issue then there is an increased chance that the issue will go unrecorded. You cannot address issues that you do not know about. It is not necessary that everyone has access to central repository, but the more you can allow the better.

Action item: Set up access to the central repository for those people that need it.

3.2 Recording

Training people to identify issues is often unnecessary, however getting people to record the issue in the central repository will take some training and encouragement. For example, a team member may mention an unrecorded issue to the project manager during a coffee break or other informal occasion, this team member needs some encouragement to record such issues in the central repository.

For all kinds of issues, prevention is better than correction. Also, issues tend to be less severe if they are addressed earlier rather than later. This means that every effort should be made to report issues as soon as they are discovered, instead of waiting for the issue to become "serious enough" before recording it. Do not be afraid of duplicating an issue or overlapping with existing issues, it is better than missing an issue.

A complete description of the cause of the issue should be recorded in the central repository. Resist the temptation to describe the issue in terms of a solution. Any implication of the issue should be recorded. Attach any supporting documentation, screenshots, report output, faxes, error messages and other media that describes the issue.

The person who is recording the issue can make a recommendation for a solution, if they have one. This person should also assign the issue if possible, even if it is only assigned to the issue manager for re-assignment.

When an issue is initially recorded it should be recorded in the central repository with a status code that reflects the fact that it is new issue and has not been reviewed. An attempt should also be made to categorize and rank the severity of the issue.

The date and who created the issue should be recorded in the central repository. This is done automatically for you in systems like Issue Tracker.

Many teams describe issues in terms of the desired solution, leaving others to deduce the actual issue. This is not best practice since it limits the scope of possible creative solutions. As an example a badly worded issue: "We need more people." There is no indication in this example of what the issue actually is, so finding alternative solutions is impossible. If the example issue had been worded as "The shipping department has swamped us with product, there is a possibility of spoilage if we cannot get the product delivered." With the issue worded this way perhaps the shipping department can become aware of how there actions are causing issues down the line and adapt their actions.

3.3 Initial Review

The initial review is a triage of new issues. It is usually performed by the issue manager or deputies who are familiar with the scope and priorities of the project. If the team is small the entire team can meet for the review. For each new issue the status, category and severity are reviewed and the issue assigned to someone for action and optionally an owner is identified as follows.

Sometimes the same person who records the issue may be doing the initial review, so these two steps can be fused into one in this situation.

3.3.1 Issue Status

A decision is made about the next state of the issue. (The previous state was "new".) The next status of the issue reflects the nature and timing of the action to address the issue. It is one of the following:

  • open: immediate action will be taken to address the issue
  • deferred: action will be deferred until some future time
  • referred: action will be taken by some other group, probably because the issue is beyond the current scope
  • cancelled: no action will be taken now or in the future

3.3.2 Categorize the issue

A first attempt at categorizing the issue was made when it was first recorded. But, now during the initial review the category can be refined.

The proper issue category is helpful when prioritizing the resources required to address issues. It is especially useful for reporting purposes.

Action item: Discuss with the team how best to categorize the issues you expect to get, and document the categories that will be used.

3.3.3 Rank the issue severity

The severity reflects the importance of getting the issue resolved. Obviously, you want to direct resources at the most important issues before the lesser ones.

Action item: Choose a small set of severity codes that have a clear ranking. For example: Trivial, Standard, Important, Critical. Some people prefer: Low, Medium, High, Very High.

3.3.4 Assignment

From the start, the next person to take action on the issue must be assigned to the issue and notified. Issue Tracker will automatically notify the person assigned to the issue via email.

If the issue description is incomplete, the issue can be assigned to the appropriate party to gather the information necessary to make the issue description clear.

Assign a person and not a group. Experience has shown that assigning issues to individuals leads to greater accountability than assigning issues to groups. An individual can be confronted about lack of progress, it is much harder to confront a group of people. A group can be represented by a group leader, so you can assign an issue to the group leader who will take action to reassign the issue to correct group member who will actually address the issue.

3.3.5 Ownership

It should be possible to decide which stakeholder is the owner of the issue. Having an issue owner is a way of recording who is accountable for the issue's resolution.

Owners must review the issues they own for progress to resolution. If the progress is not sufficient the issue manager should be told so that the situation can be remedied.

3.4 Taking Action

The process to address an issue iterates over the following sub-steps until the issue is resolved.

  • The person assigned to the issue, takes action to address the issue.
  • The person assigned to the issue, documents the action taken as an issue event in the central repository. An issue event has the person's name, the date and a description of the action taken.
  • Some issue processes require an approval step before further action can be taken. This approval should take the form of signing off on a proposal. While paper based signatures are acceptable, an automated system is better. Issue events in Issue Tracker can by used to sign off, since a user is required to log in to identify themselves, this is as good as a paper signature.
  • If there is documentation to support the action taken, like a cost-benefit analysis of a proposed system change, the supporting files are attached to the issue.
  • The process of finding a solution may help refine the issue description. This refinement should be reflected in updates to the issue description and title, as well as attaching further supporting files. It may also require that the issue be re-categorized.
  • If the next iteration is the responsibility of another person the issue is reassigned.
  • If the issue is resolved in this iteration, the status is updated to reflect the fact that the issue is inactive.

Notice that the action taken may involve reassigning the issue, changing status, refining the issue description, changing the category of the issue. All of these changes should be recorded in the central repository. Changing of status, category and severity are automatically logged for you in an automated system like Issue Tracker.

3.5 Ongoing Oversight

Consistent and continuous evaluation of issues by the issue manager and the team must take place to bring the issues to resolution. This can take place through a periodic review of all active issues in the central repository with the team and a separate review with the stakeholders.

Escalate issues as needed by re-assigning or by changing issue ownership.

Report and communicate progress on all issues to upper management and to the team, subscriptions can be used by upper management and the team to follow progress on individual issues. This reporting can be integrated into project status reporting.

Analyze issue progress and adapt actions. The central repository should be able to provide feedback on how efficiently the issues are proceeding from creation to resolution. If it is taking too long to resolve important issues, then the issue manager must find ways to improve the turn-around time.

4. Finally

The following are a few further action items

Action item: Distribute copies of this issue management methodology to team members and stakeholders so that everyone knows how and why issues are managed.

Action item: Adapt and scale this issue management methodology to suit you project's scale and quirks.

Action item: Create your central repository, and get started today.

This issue management methodology has evolved over many years. It evolved from experience on projects with budgets from $500,000 to $50,000,000 which had a total number of issues ranging from a few hundred issues to many thousands. In half the cases the project team was physically dispersed in several countries.



Shared Movies, 75% Each Sale. - Movie traffic, great seller, great conversion, Now with Google/Yahoo Tracking!
Hot* Brand New: AdwareAlert. - Our Highet Converting/Paying Designs Ever! Easy Ppc Sales! Also try SpywareRemover.com. Now with Msn/Goog/Yhoo Tracking!


Article Index: | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 | 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 | 41 | 42 | 43 | 44 | 45 | 46 | 47 | 48 | 49 | 50 | 51 | 52 | 53 | 54 | 55 | 56 | 57 | 58 | 59 | 60 | 61 | 62 | 63 | 64 | 65 | 66 | 67 | 68 | 69 | 70 | 71 | 72 | 73 | 74 | 75 | 76 | 77 | 78 | 79 | 80 | 81


More Articles:


1. What is Six Sigma Deployment By Joseph Peterka
In the implementation of Six Sigma, an effective infrastructure lays the foundation for success. An effective infrastructure for your Six Sigma or Lean Flow change initiative in an organization requires a clear strategy and comprehensive planning.Strategizing and PlanningThe planning stage of a Six Sigma deployment is where you can gain valuable traction. A critical factor in a successful deployment is the selection and chartering of the project that link to the strategy of their organization.…

2. Get It Done! Soft Skills not Hard Tools are Required By Chuck Yorke
If your organization has people, then interpersonal skills are needed.I work with companies that are on a path they call the lean journey. Whatever you call it, it’s based on the Toyota Production System. Some manufacturers embraced it and it became known as Lean Manufacturing, expanded into the Lean Office or Lean Enterprise. During this transformation the approach became focused on tools, but Toyota’s approach is about people.The focus of Lean Manufacturing training has been on technical ski…

3. Decisions, Decisions By Julane Borth
Thirty years ago, Jerry Harvey, a professor at George Washington University told a true story about an incident that occurred when he and his wife visited his in-laws in Texas one summer. On a scorching August afternoon, they were enjoying a game of dominoes and cold lemonade on a shady porch when Professor Harvey’s father-in-law suggested that they drive to Abilene and have lunch in the cafeteria. Harvey later explained that he thought it was a crazy idea, but he didn’t want to spoil everyo…

4. SINO_NSH VFD Insulation Oil Purifier/oil purification/oil treatment plant
NoneVFD(oil Treatment, oil Filtration, oil Purification, oil Recycling, oil Filter, oil Restoration, oil Regeneration, oil Filtering, oil Reclamation) series is mainly used to improve the properties of insulation oil. It can remove trace water, gas, particulate matters etc. from the insulating oil effectively and rapidly so as to boost performance of transformers, circuit breakers, mutual inductors, cable and capacitors which has insulation system. VFD series specialize in purifying branded oil,…